Tenant Row/Ketch Joanne Restroom
Project Location: | Pillar Point Harbor |
---|---|
Status: | In Permitting Phase |
Initial Funding: | September 16, 2020 |
Estimated Completion: | Underway |
Description: | Replace restrooms to be ADA Compliant |
Justification: | To provide adequate public restroom facilities |
Strategic Goal Operating Impact: | 1) Comprehensive Long-Range Planning Guides District |
2) Infrastructure Improvements are Guided by Comprehensive Long-Term Planning. |
RECENT UPDATES:
EVRA Construction Inc was determined low bidder and Notice to Proceed was issued August 9, 2022. Protective fencing was put in place on October 4, 2022.
As of Janaury 18, 2023 Construction is underway.