Surfers Beach Pilot Restoration Project/SCHEDULE
Project Engineering and Design: The project planning team prepared 30% Plans (permitting level) for the Surfers Beach Project and Eelgrass Mitigation. The team also completed a Preliminary Design Report for the Surfers Beach Project. Currently, the engineering team from ESA is coordinating with consultant Brad Damitz and District staff on revising the plans based on input from permitting agencies…